Ganga Expressway project: 95 percent of land acquisition completed
The Uttar Pradesh government has informed that 95 percent of the land acquisition is completed for the 595 km Ganga Expressway project. Further 77 percent of the land clearing and grubbing has already been completed, and the project has already acquired environmental and forest clearances. 52 percent of the utility relocation has also been completed.
The expressway project is estimated to be commissioned in the next 36 months i.e. by November 2025.