Bangalore to Vijayawada Expressway: 30 bids received for 6 packages
The National Highways Authority of India (NHAI) has informed that 8 firms have submitted a total of 30 bids for the civil construction contracts of the 518 km Bengaluru – Vijayawada Expressway project’s packages 5, 6, 11, 12, 13 & 14 in Andhra Pradesh. The expressway will be built under Bharatmala Pariyojana (BMP) Phase 2 with a mix of brownfield-upgrade (36 percent) and greenfield (64 percent) routes.
Bidders for the project are:
- Dilip Buildcon Ltd. – P5, P6, P11, P12, P13 & P14
- Dineshchandra R Agrawal Infracon Pvt. Ltd. – P11 only
- G R Infraprojects Ltd. – P5, P6, P11, P12, P13 & P14
- HG Infra Engineering Ltd. – P5, P6, P12, P13, & P14
- KCP Infra Ltd. – P12 only
- KNR Constructions Ltd. – P12, P13, & P14
- Megha Engineering and Infrastructures Ltd. – P5, P6, P11, P12, P13 & P14
- PNC Infratech Ltd. – P5 & P6
Scope of work under various packages involves:
- Package 5 (32.70 km): Nallacheruvu palli (Ch.96.300) to Yerragudipadu (Ch 129.000)
- Package 6 (31 km): Yerragudipadu (Ch.129.000) to Audireddipalle (Ch.160.000)
- Package 11 (32 km): Chandrasekharapuram (Ch.228.000) to Polavaram (Ch. 260.000)
- Package 12 (25.50 km): Polavaram (Ch. 260.000) to Marripudi (Ch.285.500)
- Package 13 (29.10 km): Marripudi (Ch. 285.500) to Somavarappadu (Ch.314.600)
- Package 14 (28.64): Somavarappadu (Ch.314.600)to Muppavaram (Ch.343.240)
Also Read: Ahmedabad To Dholera Expressway Project: Work Progressing At Fast Pace