Kamakhya Gate to Maligaon bridge: Assam chief minister to inaugurate project on 28th August
Assam state's longest road bridge from Kamakhya Gate to Maligaon in west Guwahati would be inaugurated on 28 August 2023 by the state Chief Minister Himanta Biswa Sarma. The bridge is being constructed on a 2.63 km-long stretch at a project cost of Rs 420.75 crore.
As of now foundation and sub-structure of the main bridge and Pandu's arm have been completed, while in the superstructure, only two of the 124 deck slabs are yet to be completed, as also a deck slab remains incomplete in Pandu's arm. The deadline to complete the flyover is 23 October 2023 but from 28 August 2023 itself, vehicular movement will start on it.
Also Read: Gohpur To Numaligarh Tunnel Project: Single Bidder Places Bid For Rs 6500 Crore Project