Hajipur to Bachhwara project commissioned by IRCON
The wholly owned subsidiary of the Indian Railways, Ircon International (Ircon) has informed commissioning of the doubling work of Hajipur-Bachhwara. The work involved a 72 km route including electrification.
The entire commissioning has been done in various phases i.e. commissioning of Bachhwara-Mohiudding Nagar (20 km) and Mohiudding Nagar-Sahpur Patori (13 km) has been done in the year 2020. Bachhwara yard was commissioned in the year 2021 and the commissioning of Sahpur Patori-Sahdei Buzurg (12 km), Hajipur-Akshaywat Rai Nagar (12 km) & Akshaywat Rai Nagar-Sahdei Buzurg (14 km) has been completed in the year 2022.