Khavda solar project: NGEL comisssions 49 MW capacity
NTPC's arm, NTPC Green Energy Ltd (NGEL,) has informed that the commercial supply of 49 megawatt capacity at Khavda Solar Energy Project will start from August 22nd, 2025, which is a Friday.
This marks the third part commissioning of the 300 MW project. The first part, with a capacity of 142.2 MW, and the second part, with a capacity of 32.8 MW, became commercially operational with effect from June 28 and June 30, respectively.