Hindustan Power bags order for BESS from Bihar
Independent power producer Hindustan Power has received a Letter of Intent (LoI) from Bihar State Power Generation Company Limited (BSPGCL). The LoI is for developing a 120 MWh Standalone Battery Energy Storage System (BESS) across three critical grid substations in Bihar.
Work would be done on a BOOT (Build, Own, Operate, Transfer) basis. The development would be done at Bhagalpur (40 MWh), Udakishanganj (40 MWh), and Sitamarhi (40 MWh), and the completion period would be 18 months.